From: Stuart, Ralph <Ralph.Stuart**At_Symbol_Here**KEENE.EDU>
Subject: Re: [DCHAS-L] New Science Building- Things to Look Out For
Date: Nov 20, 2017 18:38 UTC
Reply-To: ACS Division of Chemical Health and Safety <DCHAS-L**At_Symbol_Here**PRINCETON.EDU>
Message-ID: 9C5B2BE7-7549-4CE6-A748-1E72D312D86B**At_Symbol_Here**keene.edu
In-Reply-To:
> â?¢ If possible, have the contractors fully complete one lab before doing the individual parts for the whole building. If we were given the opportunity to review a fully completed lab, many issues could have been easily avoided.
>
I have seen this happen by using an off-campus mock-up. This was very helpful in clarifying for all of the stakeholders what was to be built before the building plans were finalized. I'm sure this approach improved the project significantly.
- Ralph
Ralph Stuart, CIH, CCHO
Environmental Safety Manager
Keene State College
603 358-2859
ralph.stuart**At_Symbol_Here**keene.edu
---